Project Milestone Status

Project Milestones Status

 

Project Milestone Description (Days from Appointed Date) Planned Actual Current Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 200 Days 20% 08.08.2019 24.62% 01.08.2019  
Project Milestone-II 450 Days 35% 25.12.2019 35.56% 20.12.2019  
Project Milestone-III 600 Days 75% 08.03.2021 75% 08.03.2021  
Schedule Completion 910 Days 100% 10.07.2021 100% 10.07.2021 PCOD Issued.