Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Current Status | ||
---|---|---|---|---|---|---|
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | |||
Project Milestone-I | 200 Days | 20% | 08.08.2019 | 24.62% | 01.08.2019 | |
Project Milestone-II | 450 Days | 35% | 25.12.2019 | 35.56% | 20.12.2019 | |
Project Milestone-III | 600 Days | 75% | 08.03.2021 | 75% | 08.03.2021 | |
Schedule Completion | 910 Days | 100% | 10.07.2021 | 100% | 10.07.2021 | PCOD Issued. |